Case Study 1
Highway Lane Closure
Project Overview
US-290, Harris County
Two-lane highway resurfacing requiring alternating one-way traffic control across a 1.2-mile active work zone during daytime hours.
The Challenge
TxDOT requires site-specific plans for any closure on a state highway with an ADT above 10,000. The contractor had previously submitted a generic template plan and received a rejection with 11 review comments. The project was already delayed two weeks and the crew was standing by.
TCP Edge's Solution
TCP Edge designed a fully site-specific plan using current aerial imagery of the US-290 corridor. The plan incorporated accurate taper lengths calculated for the posted 65 mph speed limit, properly spaced channelizing devices, advance warning sign placement at required distances, and a shadow vehicle specification with TMA. All 11 prior review comments were addressed in the new submittal.
Results Achieved
“We had already lost two weeks on this job. TCP Edge turned around a clean, site-specific plan fast and it sailed through TxDOT review on the first try. We will not use anyone else for our state highway work.”
Operations Manager
Regional Paving Contractor — Houston, TX